Enter rise and run, a pitch, or an angle. Get the pitch in x/12, the angle in degrees, the rafter and hip multipliers, the roof area in squares, and which roofing materials the code allows at that slope.

By ChiselJobs Team · Updated

Measurements

I know the

Measure rise and run in the same unit. A common field method: hold a level 12 inches long against the rafter and measure straight up to the underside of the roof.

Roof Pitch

Pitch

6/12

26.57° · 50% slope

Run 12Rise 626.6°

Rafter Multiplier

1.118

Hip / Valley Multiplier

1.5

Common Rafter per Ft of Run

13.42 in

Hip / Valley per Ft of Run

18 in

Roofing Allowed at This Pitch

  • Standing-seam metal panelsmin 0.25/12 · IRC R905.10.2
  • Built-up roofingmin 0.25/12 · IRC R905.9.1
  • Modified bitumenmin 0.25/12 · IRC R905.11.1
  • Lapped metal panels, with sealantmin 0.5/12 · IRC R905.10.2
  • Mineral-surfaced roll roofingmin 1/12 · IRC R905.5.2
  • Asphalt shinglesmin 2/12 · IRC R905.2.2
  • Clay and concrete tilemin 2.5/12 · IRC R905.3.2
  • Metal roof shinglesmin 3/12 · IRC R905.4.2
  • Lapped metal panels, no sealantmin 3/12 · IRC R905.10.2
  • Wood shinglesmin 3/12 · IRC R905.7.2
  • Wood shakesmin 3/12 · IRC R905.8.2
  • Slate shinglesmin 4/12 · IRC R905.6.2

What Is Roof Pitch?

Roof pitch is how many inches a roof rises for every 12 inches it runs horizontally. A 6/12 roof (said "six in twelve") climbs 6 inches over each foot of run. Carpenters work in x/12 because it maps straight onto a framing square: the 12 is the body of the square and the rise is the tongue.

The same steepness can be written three ways. Pitch is 6/12. Slope as a percentage is rise divided by run, so 6/12 is 50%. The angle is about 26.57°. Older carpentry books also use "pitch" for rise divided by the full span, which makes a 6/12 roof a "1/4 pitch" roof, so check which meaning a set of plans uses.

How to Measure Roof Pitch

There are four common ways, from easiest to most accurate.

  • From the attic: hold a level against the bottom of a rafter, mark 12 inches along the level, and measure straight up from that mark to the underside of the rafter. That number is the rise.
  • From the roof surface: set a level on the shingles, level it, and measure from the 12-inch mark down to the roof. Shingle thickness adds a little error.
  • From the gable end: measure the total rise from the top plate to the ridge and half the building width, then enter them as rise and run.
  • From the plans: the pitch is usually drawn as a small triangle on the elevations or listed in the framing notes.

Roof Pitch Formulas

Everything comes from the right triangle formed by the rise, the run and the rafter. Rise and run just need to be in the same unit.

Pitch

Pitch = rise ÷ run × 12

Angle

Angle = arctan(pitch ÷ 12)

Slope percent

Slope % = pitch ÷ 12 × 100

Rafter multiplier

M = √(pitch² + 144) ÷ 12

Hip and valley multiplier

H = √(pitch² + 288) ÷ 12

Roof area

Area = footprint × M

pitch
Rise in inches per 12 inches of run
M
Common rafter length per unit of run
H
Hip or valley rafter length per unit of common run (regular hip)
288
16.97², the diagonal run of a hip per foot of common run
footprint
Plan area including overhangs, in sq ft

One roofing square is 100 sq ft of roof surface. The area formula assumes every roof plane has the same pitch.

Worked Example: Pitch From a Measurement

From the attic, you measure 4 inches of rise over 10 inches of run.

  1. Pitch: 4 ÷ 10 × 12 = 4.8/12.
  2. Angle: arctan(4 ÷ 10) = 21.80°.
  3. Slope: 4.8 ÷ 12 = 40.0%.

Result: about 4.8/12, or 21.80°. That is above the 4/12 line, so asphalt shingles need only a single layer of underlayment.

Worked Example: Roofing Squares for a 7/12 Roof

A house has a 1,800 sq ft footprint including overhangs and a 7/12 roof on every plane. How much roofing is needed?

  1. Rafter multiplier: √(7² + 144) ÷ 12 = √193 ÷ 12 = 1.1577.
  2. Roof area: 1,800 × 1.1577 = 2,084 sq ft.
  3. Squares: 2,084 ÷ 100 = 20.84 squares.

Result: about 20.84 squares before waste. Add more for hips, valleys and starter courses.

Roof Pitch to Degrees Chart

Common pitches with their angle, slope, and rafter and hip multipliers.

Calculated from the formulas above. Multipliers match the rafter table on a steel framing square.
PitchAngleSlopeRafter ×Hip / valley ×
1/124.76°8.3%1.00351.4167
2/129.46°16.7%1.01381.4240
3/1214.04°25.0%1.03081.4361
4/1218.43°33.3%1.05411.4530
5/1222.62°41.7%1.08331.4743
6/1226.57°50.0%1.11801.5000
7/1230.26°58.3%1.15771.5298
8/1233.69°66.7%1.20191.5635
9/1236.87°75.0%1.25001.6008
10/1239.81°83.3%1.30171.6415
11/1242.51°91.7%1.35661.6853
12/1245.00°100.0%1.41421.7321
14/1249.40°116.7%1.53661.8333
16/1253.13°133.3%1.66671.9437
18/1256.31°150.0%1.80282.0616
24/1263.43°200.0%2.23612.4495

Minimum Roof Pitch by Roofing Material

The International Residential Code sets a minimum slope for each roof covering. Manufacturer instructions can require more.

Source: International Residential Code, Section R905. Local amendments may differ.
Roof coveringMinimum pitchIRC sectionNote
Standing-seam metal panels0.25/12R905.10.2
Built-up roofing0.25/12R905.9.1
Modified bitumen0.25/12R905.11.1
Lapped metal panels, with sealant0.5/12R905.10.2
Mineral-surfaced roll roofing1/12R905.5.2
Asphalt shingles2/12R905.2.2Double underlayment below 4/12
Clay and concrete tile2.5/12R905.3.2Double underlayment below 4/12
Metal roof shingles3/12R905.4.2
Lapped metal panels, no sealant3/12R905.10.2
Wood shingles3/12R905.7.2
Wood shakes3/12R905.8.2
Slate shingles4/12R905.6.2

Low-Slope, Conventional and Steep Roofs

OSHA defines a low-slope roof as 4/12 or less and a steep roof as anything above 4/12 (29 CFR 1926.500). Most houses in North America land between 4/12 and 9/12, which sheds water and snow well and is still workable from the roof surface with care.

Steeper roofs give more attic space and a traditional look but take more material, need roof jacks or staging to work on, and cost more labor per square. Below 4/12, the code limits which coverings you can use and often requires extra underlayment, as the table above shows.

Field Tips

Practical advice from framers and roofers on ContractorTalk, RoofingTalk, Fine Homebuilding and JLC, checked against the IRC and OSHA.

  1. 1

    Measure over a long run

    A 12-inch level is fine for a quick read, but a small error at 12 inches turns into a big one over a whole rafter. For framing, measure the overall rise and run. A digital angle finder or smart level that reads pitch directly is faster and often more accurate.

  2. 2

    Most roofers stop walking around 7/12 or 8/12

    Many crews switch to toe boards or roof jacks at about 7/12, set jacks every 6 to 8 courses on steeper roofs, and use level 2x8 planks instead of 2x6. These are crew habits, not code, so set your own limit by the roof and the weather.

  3. 3

    Fall protection starts at 6 feet

    OSHA requires guardrails, safety nets or personal fall arrest for residential construction work 6 feet or more above a lower level (29 CFR 1926.501(b)(13)), whatever the pitch. A harness is clumsy on a steep roof but it is the rule, and it's what keeps a slip from becoming a fall.

  4. 4

    Ice barrier length grows with pitch

    Where the IRC requires an ice barrier, it must run from the eave to a point 24 inches inside the exterior wall line. That 24 inches is measured horizontally, so the membrane is longer along a steep roof. With a 12-inch overhang and a 6-inch wall, that's 42 inches of horizontal run, and on a 6/12 roof it takes about 47 inches of membrane (42 × 1.118), more than one 36-inch roll.

  5. 5

    Steep work costs more per square

    Roofers and insurance estimating software commonly price steep work in bands: 7/12 to 9/12, 10/12 to 12/12, and above 12/12. Use the pitch from this calculator to put a job in the right band before you bid it.

Sources: Fine Homebuilding: How to find the pitch of an existing roof, ContractorTalk: Measuring roof slope, ContractorTalk: Pitch, when to stop walking, OSHA 1926.501, Fine Homebuilding: Ice-dam protection, how far up the roof?, JLC: Ice dam membrane at eaves, RoofingTalk: What are you charging?, ContractorTalk: How do you charge for tear off?

Frequently Asked Questions